The renovation of the Flamingo Spa’s washrooms was completed on schedule – The success was due to careful control of the conditions

The renovation of the Flamingo Spa’s washrooms was completed on schedule – The success was due to careful control of the conditions

The extensive renovation of the men’s changing rooms at Flamingo Spa was completed on a tight schedule thanks to the seamless collaboration between Kymppirakenne and Vertia. The project involved the renewal of all surfaces, and the drying phase in particular played a crucial role, as the coating work determined the progress of the entire project.

A Critical Phase: Humidity Control in Spa Environments

Renovating washrooms in a spa environment places exceptional demands on moisture control. In the Kymppirakente project, the greatest risks were related to the drying of structures, the adequacy of moisture removal, and the control of conditions when moist air from adjacent spa facilities in use entered the negative-pressure washroom. In addition, organizing humidity measurements and ensuring rapid access to results were essential so that decisions could be made without delay.

“The drying process was a critical phase, as the coating work dictated the timing of all other work phases. The schedule was tight, and there was no room for uncertainty,” says the site foreman Antti Korhonen.

Vertia's solution: effective environmental control and rapid response

Vertia was fully responsible for managing the environmental conditions throughout the project. A wide range of dehumidifiers and fans was used, and conditions were monitored continuously. Additional equipment was brought to the site as needed to ensure that the drying process proceeded according to schedule.

Condition control included:

  • effective moisture removal
  • improving ventilation
  • coordination of continuous monitoring and measurements
  • the ability to respond quickly to changing situations

This approach ensured that the structures dried safely and as expected.

The drying process went very well – The coating work began on schedule

All surfaces dried according to schedule and even faster than expected. This was one of the project’s key successes, as any delay in the coating work would have affected the completion of the entire project.

“The drying process went really well. We were able to start the coating work exactly as planned, which was critical to the success of the entire project.”

Our long-standing partnership provided reassurance

Kymppirakenne has been collaborating with Vertia since 2021, particularly in the areas of humidity measurement and environmental control. The experience has been consistently positive.

“The service has been spot-on every time. Rating: 5/5.”

Recommendation: This solution works for all time-sensitive projects

Kymppirakenne recommends a comprehensive solution for environmental control and monitoring, particularly for projects where staying on schedule is essential.

“I would definitely recommend them. When you’re working to a tight schedule, a partner like this provides peace of mind and predictability.”