The renovation of the Flamingo Spa’s washrooms was completed on schedule – The success was due to careful control of the conditions
The extensive renovation of the men’s changing rooms at Flamingo Spa was completed on a tight schedule thanks to the seamless collaboration between Kymppirakenne and Vertia. The project involved the renewal of all surfaces, and the drying phase in particular played a crucial role, as the coating work determined the progress of the entire project. Critical phase: moisture control in a spa environment Renovating washrooms in a spa environment places exceptional demands on moisture control. In Kymppirakenne’s project, the greatest risks were related to the drying of structures, the adequacy of moisture removal, and the conditions Read more about The renovation of the Flamingo Spa’s washrooms was completed on schedule – The success was due to careful control of the conditions[…]